OCS Installs Heat Pump at Whitecraig Primary

2 Minute Read

Services

Hard Services

Key Criteria

Productivity

Region

Scotland

East Lothian Council logo featuring a stylized blue bird in flight above the words East Lothian Council in blue text.
Two women, one older and one younger, sit at a classroom table with papers in front of them, engaged in a friendly conversation. The room has white walls, a closed door, and natural light coming in.

Executive Summary

OCS supported Morrison Construction in delivering a new primary school in Whitecraig, East Lothian, on behalf of East Lothian Council. We installed all mechanical, electrical, plumbing, data, and fire protection systems, including a complex air source heat pump system designed by Harley Haddow.

By proposing an off-site fabrication approach, we overcame logistical, safety, and environmental challenges. We completed the full on-site installation within one day, reducing disruption, improving safety and keeping the build on schedule.

The Brief

East Lothian Council commissioned a purpose-built primary school in Whitecraig to provide a modern learning environment and meet the area’s growing demand for places.

A key requirement was the installation of an air-source heat-pump system situated on a remote, purpose-built frame outside the main building. The system demanded extensive welded steel pipework to distribute heating and hot water throughout the school.

 

Deliver full MEP, data, and fire protection installations.
Install an air source heat pump system on a remote frame.
Keep the project on schedule and reduce health and safety risks.
Avoid weather-related delays and minimise site disruption.
Large pipelines run parallel to each other across a grassy area at sunset, with power lines and transmission towers visible in the background under an orange sky.

The Outcome

By shifting the heat pump installation off-site, we reduced on-site work from several weeks to one day. Our approach eliminated hot works and weather risks, improved safety, and allowed Morrison Construction to maintain programme timelines. We preserved the design intent while delivering a high-efficiency solution that aligned with the council’s sustainability goals.

  • Programme certainty: Installation time on site reduced by an estimated six to eight weeks, freeing resources for other trades and protecting the overall build schedule.

  • Improved safety: Elimination of on-site hot works reduced risk and simplified safety oversight for Morrison Construction.

  • Weather resilience: Fabrication in a controlled environment removed dependence on outdoor conditions, ensuring predictable delivery.

  • Sustainability maintained: The off-site approach preserved the energy-efficient design created by Harley Haddow, supporting East Lothian Council’s low-carbon objectives.